How to repair/replace old tongue and groove plank subfloor in bathroom?












5















After my bathroom was demoed, I discovered that the subfloor is in bad shape. The home was built in the 1960s and the subfloor consists of 3/4" thick tongue and groove planks running diagonal to the joists. I do not know if it was poorly constructed or if this naturally happened over time, but the tongues and grooves of the planks across much of the floor are no longer nesting within each other. As such, the floor does not have much structural integrity.



As you can see in the photo below, a section of the floor broke away easily during demo. There are other sections that flex so much that I feel like I'd break through if I attempted to put my full weight on it.



This is a bathroom that will have a tile floor so the goal is to properly support the tile, a bathtub, etc.. Outside the bathroom is 3/4" hardwood and I'd prefer not having too much of a differential with this.



I have had a few contractors present some different approaches that include cutting out the old floor and completely replacing it or simply adding a thin layer of new plywood on top of the old floor. The thin layer on top seems like the simplest approach but I have concerns with both building on top of a questionable old floor as well as about the extra height (what would be the minimum acceptable thickness for the new layer in this case?).



What is the proper way to repair this floor?



Broken floor



Close up of gaps










share|improve this question























  • Are the floor boards rotting?

    – BlueJay
    8 hours ago











  • They are not rotting in terms of any sort of damage from water. I'd say the individual planks are in decent shape, but there are quite a few spots where they seem a bit soft either from knots or I guess having to deal with extra weight in some spots such as right in front of the toilet.

    – David Anderson
    8 hours ago











  • It looks like many of them have shrunk, and don't even touch each other anymore. Are those area over any old leaks, or somewhere that was often wet, like right outside a shower or tub?

    – Xen2050
    2 hours ago
















5















After my bathroom was demoed, I discovered that the subfloor is in bad shape. The home was built in the 1960s and the subfloor consists of 3/4" thick tongue and groove planks running diagonal to the joists. I do not know if it was poorly constructed or if this naturally happened over time, but the tongues and grooves of the planks across much of the floor are no longer nesting within each other. As such, the floor does not have much structural integrity.



As you can see in the photo below, a section of the floor broke away easily during demo. There are other sections that flex so much that I feel like I'd break through if I attempted to put my full weight on it.



This is a bathroom that will have a tile floor so the goal is to properly support the tile, a bathtub, etc.. Outside the bathroom is 3/4" hardwood and I'd prefer not having too much of a differential with this.



I have had a few contractors present some different approaches that include cutting out the old floor and completely replacing it or simply adding a thin layer of new plywood on top of the old floor. The thin layer on top seems like the simplest approach but I have concerns with both building on top of a questionable old floor as well as about the extra height (what would be the minimum acceptable thickness for the new layer in this case?).



What is the proper way to repair this floor?



Broken floor



Close up of gaps










share|improve this question























  • Are the floor boards rotting?

    – BlueJay
    8 hours ago











  • They are not rotting in terms of any sort of damage from water. I'd say the individual planks are in decent shape, but there are quite a few spots where they seem a bit soft either from knots or I guess having to deal with extra weight in some spots such as right in front of the toilet.

    – David Anderson
    8 hours ago











  • It looks like many of them have shrunk, and don't even touch each other anymore. Are those area over any old leaks, or somewhere that was often wet, like right outside a shower or tub?

    – Xen2050
    2 hours ago














5












5








5








After my bathroom was demoed, I discovered that the subfloor is in bad shape. The home was built in the 1960s and the subfloor consists of 3/4" thick tongue and groove planks running diagonal to the joists. I do not know if it was poorly constructed or if this naturally happened over time, but the tongues and grooves of the planks across much of the floor are no longer nesting within each other. As such, the floor does not have much structural integrity.



As you can see in the photo below, a section of the floor broke away easily during demo. There are other sections that flex so much that I feel like I'd break through if I attempted to put my full weight on it.



This is a bathroom that will have a tile floor so the goal is to properly support the tile, a bathtub, etc.. Outside the bathroom is 3/4" hardwood and I'd prefer not having too much of a differential with this.



I have had a few contractors present some different approaches that include cutting out the old floor and completely replacing it or simply adding a thin layer of new plywood on top of the old floor. The thin layer on top seems like the simplest approach but I have concerns with both building on top of a questionable old floor as well as about the extra height (what would be the minimum acceptable thickness for the new layer in this case?).



What is the proper way to repair this floor?



Broken floor



Close up of gaps










share|improve this question














After my bathroom was demoed, I discovered that the subfloor is in bad shape. The home was built in the 1960s and the subfloor consists of 3/4" thick tongue and groove planks running diagonal to the joists. I do not know if it was poorly constructed or if this naturally happened over time, but the tongues and grooves of the planks across much of the floor are no longer nesting within each other. As such, the floor does not have much structural integrity.



As you can see in the photo below, a section of the floor broke away easily during demo. There are other sections that flex so much that I feel like I'd break through if I attempted to put my full weight on it.



This is a bathroom that will have a tile floor so the goal is to properly support the tile, a bathtub, etc.. Outside the bathroom is 3/4" hardwood and I'd prefer not having too much of a differential with this.



I have had a few contractors present some different approaches that include cutting out the old floor and completely replacing it or simply adding a thin layer of new plywood on top of the old floor. The thin layer on top seems like the simplest approach but I have concerns with both building on top of a questionable old floor as well as about the extra height (what would be the minimum acceptable thickness for the new layer in this case?).



What is the proper way to repair this floor?



Broken floor



Close up of gaps







bathroom subfloor






share|improve this question













share|improve this question











share|improve this question




share|improve this question










asked 8 hours ago









David AndersonDavid Anderson

1434




1434













  • Are the floor boards rotting?

    – BlueJay
    8 hours ago











  • They are not rotting in terms of any sort of damage from water. I'd say the individual planks are in decent shape, but there are quite a few spots where they seem a bit soft either from knots or I guess having to deal with extra weight in some spots such as right in front of the toilet.

    – David Anderson
    8 hours ago











  • It looks like many of them have shrunk, and don't even touch each other anymore. Are those area over any old leaks, or somewhere that was often wet, like right outside a shower or tub?

    – Xen2050
    2 hours ago



















  • Are the floor boards rotting?

    – BlueJay
    8 hours ago











  • They are not rotting in terms of any sort of damage from water. I'd say the individual planks are in decent shape, but there are quite a few spots where they seem a bit soft either from knots or I guess having to deal with extra weight in some spots such as right in front of the toilet.

    – David Anderson
    8 hours ago











  • It looks like many of them have shrunk, and don't even touch each other anymore. Are those area over any old leaks, or somewhere that was often wet, like right outside a shower or tub?

    – Xen2050
    2 hours ago

















Are the floor boards rotting?

– BlueJay
8 hours ago





Are the floor boards rotting?

– BlueJay
8 hours ago













They are not rotting in terms of any sort of damage from water. I'd say the individual planks are in decent shape, but there are quite a few spots where they seem a bit soft either from knots or I guess having to deal with extra weight in some spots such as right in front of the toilet.

– David Anderson
8 hours ago





They are not rotting in terms of any sort of damage from water. I'd say the individual planks are in decent shape, but there are quite a few spots where they seem a bit soft either from knots or I guess having to deal with extra weight in some spots such as right in front of the toilet.

– David Anderson
8 hours ago













It looks like many of them have shrunk, and don't even touch each other anymore. Are those area over any old leaks, or somewhere that was often wet, like right outside a shower or tub?

– Xen2050
2 hours ago





It looks like many of them have shrunk, and don't even touch each other anymore. Are those area over any old leaks, or somewhere that was often wet, like right outside a shower or tub?

– Xen2050
2 hours ago










3 Answers
3






active

oldest

votes


















4














I wouldn't chance going over it either. If it's easily breaking and giving when you walk on it, replace it with new T&G sub flooring. Otherwise, you are going to have a bunch of cracked tiles. You might even have some floor joist issues to deal with and you can't really find trhat out without removing the old sub flooring.



You can start by cutting as close to the wall as you can with a skill saw. Set the saw depth just low enough to get through the existing sub floor. The circular saw will not get right against the wall because of the guard. You will need to use a reciprocating saw, jigsaw or a Bosch Starlock Plus or Starlock Max.. Once all of the old flooring is removed. Make sure all nails & screws are removed and the tops of the joists are clean and level. Install the new sub flooring with liquid nails on each joist.



If you run into joist issues you'll need to ask another question.






share|improve this answer

































    2














    The following options will perform equally, their differences are time, cost, and thickness of the subfloor. Best case scenario you'll still have a 3/4" subfloor, worst case you'll have 1 1/4" (sorted most economical in cost/time to least):




    1. Lay 1/2 or (preferably) 5/8 over the existing floor. It's simple, and should provide enough strength with the existing strips to support tile.


    2. Replace the strips that are weakened (you should be able to find a piece of 3/4 that would fit the space. All strips should cross a minimum of three joists for strength.
      Follow up by laying 1/2" or 5/8" on top.


    3. Remove and replace. This is a challenging option, those strips probably cross the entire house, that this means is that the walls are resting on the strips. When you remove the existing strips it will cause sagging in adjacent rooms so you'll need to at least block out beneath the walls/between joists to support the flooring on the other side. You'll also have to block out in between joists, and at the edges where the joists are more than a couple of inches away from the bathroom wall.



    Once you've blocked out the floor reinforcements take a look at the joist spacing.



    Subfloor replacement selection - OSB or Plywood. For tile, plywood is generally recommended by manufacturers over OSB.



    Picking sheathing



    Not all sheathing is created equal, however if you're picking up sheathing grade from a big box store, they hold a respectable graded sheet which is what I'm going to base the rest on.



    What's your joist spacing? What is the nominal size of the joist?
    If it's 18" and 2x8 (most likely case) or greater, you can probably get away with one 3/4, but I'd recommend 2-5/8" cross installed. If it's 16" and under, you'll be fine with a single 3/4"



    If you're going to lay sheathing on the existing floor, you need a minimum (emphasis on minimum) of 3/8". Whether it's T&G or not, anything less than 3/8 is a waste of money as it's not structural.



    Install



    Either t&g, or square edge is fine, what's important is to space them 1/8" apart (use something that's credit card thickness for spacing). Ideally glued in the seam if it's t&g, and to the joist using an ASTM D3498, or APA AFG-01 conforming adhesive (PL-400/Premium, Lumber Lock, AdvanTech for example). before applying the glue, make sure all surfaces are clean and dry.



    Cutting and Blocking



    There aren't any perfect videos, however for the preparation this video has great considerations:
    https://www.youtube.com/watch?v=CgWtHSsww-4



    Notes about blocking, use a minimum of 2x6. If you're going to use screws, I'd suggest structural screws like these



    Otherwise 16d common nails will work.



    End product should look like this





    Sources



    Ditra install guideline (they guarantee replacement if tiles crack so they'll give safe numbers) bottom of page 7 for your setup:
    https://sccpublic.s3-external-1.amazonaws.com/sys-master/images/h71/h71/8858545389598/DITRA%20Installation%20Handbook.pdf



    Page six for the bare minimum required for sheathing based on joist spacing: http://www.tolko.com/system/resources/W1siZiIsIjIwMTcvMDEvMTgvMTBfMjFfMzNfMjM3X0FQQV9FbmdpbmVlcmVkX1dvb2RfRmxvb3JfU3lzdGVtc19Db25zdHJ1Y3Rpb25fR3VpZGUucGRmIl1d/APA-Engineered%20Wood%20Floor%20Systems-Construction%20Guide.pdf






    share|improve this answer


























    • What does "block out in between joists, and at the edges" mean, or look like?

      – Xen2050
      1 hour ago











    • @Xen2050 I've added details, I was hoping for a good video on it, however they are all missing key points which I've commented on, and added a picture for reference.

      – Chris
      40 mins ago



















    0














    Cost is the biggest issue. Replacing it completely is the obvious choice. That's expensive. You can easily add 1/4" ply glued and screwed down and it will be totally structurally safe. You may however get squeaky, spongey floors. If you can fit it in your budget redo it with a new flooring material especially if you are going with tile.



    It's often less expensive to do it right once.






    share|improve this answer








    New contributor




    Joe Fala is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
    Check out our Code of Conduct.




















      Your Answer








      StackExchange.ready(function() {
      var channelOptions = {
      tags: "".split(" "),
      id: "73"
      };
      initTagRenderer("".split(" "), "".split(" "), channelOptions);

      StackExchange.using("externalEditor", function() {
      // Have to fire editor after snippets, if snippets enabled
      if (StackExchange.settings.snippets.snippetsEnabled) {
      StackExchange.using("snippets", function() {
      createEditor();
      });
      }
      else {
      createEditor();
      }
      });

      function createEditor() {
      StackExchange.prepareEditor({
      heartbeatType: 'answer',
      autoActivateHeartbeat: false,
      convertImagesToLinks: false,
      noModals: true,
      showLowRepImageUploadWarning: true,
      reputationToPostImages: null,
      bindNavPrevention: true,
      postfix: "",
      imageUploader: {
      brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
      contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
      allowUrls: true
      },
      noCode: true, onDemand: true,
      discardSelector: ".discard-answer"
      ,immediatelyShowMarkdownHelp:true
      });


      }
      });














      draft saved

      draft discarded


















      StackExchange.ready(
      function () {
      StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fdiy.stackexchange.com%2fquestions%2f157845%2fhow-to-repair-replace-old-tongue-and-groove-plank-subfloor-in-bathroom%23new-answer', 'question_page');
      }
      );

      Post as a guest















      Required, but never shown

























      3 Answers
      3






      active

      oldest

      votes








      3 Answers
      3






      active

      oldest

      votes









      active

      oldest

      votes






      active

      oldest

      votes









      4














      I wouldn't chance going over it either. If it's easily breaking and giving when you walk on it, replace it with new T&G sub flooring. Otherwise, you are going to have a bunch of cracked tiles. You might even have some floor joist issues to deal with and you can't really find trhat out without removing the old sub flooring.



      You can start by cutting as close to the wall as you can with a skill saw. Set the saw depth just low enough to get through the existing sub floor. The circular saw will not get right against the wall because of the guard. You will need to use a reciprocating saw, jigsaw or a Bosch Starlock Plus or Starlock Max.. Once all of the old flooring is removed. Make sure all nails & screws are removed and the tops of the joists are clean and level. Install the new sub flooring with liquid nails on each joist.



      If you run into joist issues you'll need to ask another question.






      share|improve this answer






























        4














        I wouldn't chance going over it either. If it's easily breaking and giving when you walk on it, replace it with new T&G sub flooring. Otherwise, you are going to have a bunch of cracked tiles. You might even have some floor joist issues to deal with and you can't really find trhat out without removing the old sub flooring.



        You can start by cutting as close to the wall as you can with a skill saw. Set the saw depth just low enough to get through the existing sub floor. The circular saw will not get right against the wall because of the guard. You will need to use a reciprocating saw, jigsaw or a Bosch Starlock Plus or Starlock Max.. Once all of the old flooring is removed. Make sure all nails & screws are removed and the tops of the joists are clean and level. Install the new sub flooring with liquid nails on each joist.



        If you run into joist issues you'll need to ask another question.






        share|improve this answer




























          4












          4








          4







          I wouldn't chance going over it either. If it's easily breaking and giving when you walk on it, replace it with new T&G sub flooring. Otherwise, you are going to have a bunch of cracked tiles. You might even have some floor joist issues to deal with and you can't really find trhat out without removing the old sub flooring.



          You can start by cutting as close to the wall as you can with a skill saw. Set the saw depth just low enough to get through the existing sub floor. The circular saw will not get right against the wall because of the guard. You will need to use a reciprocating saw, jigsaw or a Bosch Starlock Plus or Starlock Max.. Once all of the old flooring is removed. Make sure all nails & screws are removed and the tops of the joists are clean and level. Install the new sub flooring with liquid nails on each joist.



          If you run into joist issues you'll need to ask another question.






          share|improve this answer















          I wouldn't chance going over it either. If it's easily breaking and giving when you walk on it, replace it with new T&G sub flooring. Otherwise, you are going to have a bunch of cracked tiles. You might even have some floor joist issues to deal with and you can't really find trhat out without removing the old sub flooring.



          You can start by cutting as close to the wall as you can with a skill saw. Set the saw depth just low enough to get through the existing sub floor. The circular saw will not get right against the wall because of the guard. You will need to use a reciprocating saw, jigsaw or a Bosch Starlock Plus or Starlock Max.. Once all of the old flooring is removed. Make sure all nails & screws are removed and the tops of the joists are clean and level. Install the new sub flooring with liquid nails on each joist.



          If you run into joist issues you'll need to ask another question.







          share|improve this answer














          share|improve this answer



          share|improve this answer








          edited 7 hours ago

























          answered 8 hours ago









          Jerry_ContraryJerry_Contrary

          1,898315




          1,898315

























              2














              The following options will perform equally, their differences are time, cost, and thickness of the subfloor. Best case scenario you'll still have a 3/4" subfloor, worst case you'll have 1 1/4" (sorted most economical in cost/time to least):




              1. Lay 1/2 or (preferably) 5/8 over the existing floor. It's simple, and should provide enough strength with the existing strips to support tile.


              2. Replace the strips that are weakened (you should be able to find a piece of 3/4 that would fit the space. All strips should cross a minimum of three joists for strength.
                Follow up by laying 1/2" or 5/8" on top.


              3. Remove and replace. This is a challenging option, those strips probably cross the entire house, that this means is that the walls are resting on the strips. When you remove the existing strips it will cause sagging in adjacent rooms so you'll need to at least block out beneath the walls/between joists to support the flooring on the other side. You'll also have to block out in between joists, and at the edges where the joists are more than a couple of inches away from the bathroom wall.



              Once you've blocked out the floor reinforcements take a look at the joist spacing.



              Subfloor replacement selection - OSB or Plywood. For tile, plywood is generally recommended by manufacturers over OSB.



              Picking sheathing



              Not all sheathing is created equal, however if you're picking up sheathing grade from a big box store, they hold a respectable graded sheet which is what I'm going to base the rest on.



              What's your joist spacing? What is the nominal size of the joist?
              If it's 18" and 2x8 (most likely case) or greater, you can probably get away with one 3/4, but I'd recommend 2-5/8" cross installed. If it's 16" and under, you'll be fine with a single 3/4"



              If you're going to lay sheathing on the existing floor, you need a minimum (emphasis on minimum) of 3/8". Whether it's T&G or not, anything less than 3/8 is a waste of money as it's not structural.



              Install



              Either t&g, or square edge is fine, what's important is to space them 1/8" apart (use something that's credit card thickness for spacing). Ideally glued in the seam if it's t&g, and to the joist using an ASTM D3498, or APA AFG-01 conforming adhesive (PL-400/Premium, Lumber Lock, AdvanTech for example). before applying the glue, make sure all surfaces are clean and dry.



              Cutting and Blocking



              There aren't any perfect videos, however for the preparation this video has great considerations:
              https://www.youtube.com/watch?v=CgWtHSsww-4



              Notes about blocking, use a minimum of 2x6. If you're going to use screws, I'd suggest structural screws like these



              Otherwise 16d common nails will work.



              End product should look like this





              Sources



              Ditra install guideline (they guarantee replacement if tiles crack so they'll give safe numbers) bottom of page 7 for your setup:
              https://sccpublic.s3-external-1.amazonaws.com/sys-master/images/h71/h71/8858545389598/DITRA%20Installation%20Handbook.pdf



              Page six for the bare minimum required for sheathing based on joist spacing: http://www.tolko.com/system/resources/W1siZiIsIjIwMTcvMDEvMTgvMTBfMjFfMzNfMjM3X0FQQV9FbmdpbmVlcmVkX1dvb2RfRmxvb3JfU3lzdGVtc19Db25zdHJ1Y3Rpb25fR3VpZGUucGRmIl1d/APA-Engineered%20Wood%20Floor%20Systems-Construction%20Guide.pdf






              share|improve this answer


























              • What does "block out in between joists, and at the edges" mean, or look like?

                – Xen2050
                1 hour ago











              • @Xen2050 I've added details, I was hoping for a good video on it, however they are all missing key points which I've commented on, and added a picture for reference.

                – Chris
                40 mins ago
















              2














              The following options will perform equally, their differences are time, cost, and thickness of the subfloor. Best case scenario you'll still have a 3/4" subfloor, worst case you'll have 1 1/4" (sorted most economical in cost/time to least):




              1. Lay 1/2 or (preferably) 5/8 over the existing floor. It's simple, and should provide enough strength with the existing strips to support tile.


              2. Replace the strips that are weakened (you should be able to find a piece of 3/4 that would fit the space. All strips should cross a minimum of three joists for strength.
                Follow up by laying 1/2" or 5/8" on top.


              3. Remove and replace. This is a challenging option, those strips probably cross the entire house, that this means is that the walls are resting on the strips. When you remove the existing strips it will cause sagging in adjacent rooms so you'll need to at least block out beneath the walls/between joists to support the flooring on the other side. You'll also have to block out in between joists, and at the edges where the joists are more than a couple of inches away from the bathroom wall.



              Once you've blocked out the floor reinforcements take a look at the joist spacing.



              Subfloor replacement selection - OSB or Plywood. For tile, plywood is generally recommended by manufacturers over OSB.



              Picking sheathing



              Not all sheathing is created equal, however if you're picking up sheathing grade from a big box store, they hold a respectable graded sheet which is what I'm going to base the rest on.



              What's your joist spacing? What is the nominal size of the joist?
              If it's 18" and 2x8 (most likely case) or greater, you can probably get away with one 3/4, but I'd recommend 2-5/8" cross installed. If it's 16" and under, you'll be fine with a single 3/4"



              If you're going to lay sheathing on the existing floor, you need a minimum (emphasis on minimum) of 3/8". Whether it's T&G or not, anything less than 3/8 is a waste of money as it's not structural.



              Install



              Either t&g, or square edge is fine, what's important is to space them 1/8" apart (use something that's credit card thickness for spacing). Ideally glued in the seam if it's t&g, and to the joist using an ASTM D3498, or APA AFG-01 conforming adhesive (PL-400/Premium, Lumber Lock, AdvanTech for example). before applying the glue, make sure all surfaces are clean and dry.



              Cutting and Blocking



              There aren't any perfect videos, however for the preparation this video has great considerations:
              https://www.youtube.com/watch?v=CgWtHSsww-4



              Notes about blocking, use a minimum of 2x6. If you're going to use screws, I'd suggest structural screws like these



              Otherwise 16d common nails will work.



              End product should look like this





              Sources



              Ditra install guideline (they guarantee replacement if tiles crack so they'll give safe numbers) bottom of page 7 for your setup:
              https://sccpublic.s3-external-1.amazonaws.com/sys-master/images/h71/h71/8858545389598/DITRA%20Installation%20Handbook.pdf



              Page six for the bare minimum required for sheathing based on joist spacing: http://www.tolko.com/system/resources/W1siZiIsIjIwMTcvMDEvMTgvMTBfMjFfMzNfMjM3X0FQQV9FbmdpbmVlcmVkX1dvb2RfRmxvb3JfU3lzdGVtc19Db25zdHJ1Y3Rpb25fR3VpZGUucGRmIl1d/APA-Engineered%20Wood%20Floor%20Systems-Construction%20Guide.pdf






              share|improve this answer


























              • What does "block out in between joists, and at the edges" mean, or look like?

                – Xen2050
                1 hour ago











              • @Xen2050 I've added details, I was hoping for a good video on it, however they are all missing key points which I've commented on, and added a picture for reference.

                – Chris
                40 mins ago














              2












              2








              2







              The following options will perform equally, their differences are time, cost, and thickness of the subfloor. Best case scenario you'll still have a 3/4" subfloor, worst case you'll have 1 1/4" (sorted most economical in cost/time to least):




              1. Lay 1/2 or (preferably) 5/8 over the existing floor. It's simple, and should provide enough strength with the existing strips to support tile.


              2. Replace the strips that are weakened (you should be able to find a piece of 3/4 that would fit the space. All strips should cross a minimum of three joists for strength.
                Follow up by laying 1/2" or 5/8" on top.


              3. Remove and replace. This is a challenging option, those strips probably cross the entire house, that this means is that the walls are resting on the strips. When you remove the existing strips it will cause sagging in adjacent rooms so you'll need to at least block out beneath the walls/between joists to support the flooring on the other side. You'll also have to block out in between joists, and at the edges where the joists are more than a couple of inches away from the bathroom wall.



              Once you've blocked out the floor reinforcements take a look at the joist spacing.



              Subfloor replacement selection - OSB or Plywood. For tile, plywood is generally recommended by manufacturers over OSB.



              Picking sheathing



              Not all sheathing is created equal, however if you're picking up sheathing grade from a big box store, they hold a respectable graded sheet which is what I'm going to base the rest on.



              What's your joist spacing? What is the nominal size of the joist?
              If it's 18" and 2x8 (most likely case) or greater, you can probably get away with one 3/4, but I'd recommend 2-5/8" cross installed. If it's 16" and under, you'll be fine with a single 3/4"



              If you're going to lay sheathing on the existing floor, you need a minimum (emphasis on minimum) of 3/8". Whether it's T&G or not, anything less than 3/8 is a waste of money as it's not structural.



              Install



              Either t&g, or square edge is fine, what's important is to space them 1/8" apart (use something that's credit card thickness for spacing). Ideally glued in the seam if it's t&g, and to the joist using an ASTM D3498, or APA AFG-01 conforming adhesive (PL-400/Premium, Lumber Lock, AdvanTech for example). before applying the glue, make sure all surfaces are clean and dry.



              Cutting and Blocking



              There aren't any perfect videos, however for the preparation this video has great considerations:
              https://www.youtube.com/watch?v=CgWtHSsww-4



              Notes about blocking, use a minimum of 2x6. If you're going to use screws, I'd suggest structural screws like these



              Otherwise 16d common nails will work.



              End product should look like this





              Sources



              Ditra install guideline (they guarantee replacement if tiles crack so they'll give safe numbers) bottom of page 7 for your setup:
              https://sccpublic.s3-external-1.amazonaws.com/sys-master/images/h71/h71/8858545389598/DITRA%20Installation%20Handbook.pdf



              Page six for the bare minimum required for sheathing based on joist spacing: http://www.tolko.com/system/resources/W1siZiIsIjIwMTcvMDEvMTgvMTBfMjFfMzNfMjM3X0FQQV9FbmdpbmVlcmVkX1dvb2RfRmxvb3JfU3lzdGVtc19Db25zdHJ1Y3Rpb25fR3VpZGUucGRmIl1d/APA-Engineered%20Wood%20Floor%20Systems-Construction%20Guide.pdf






              share|improve this answer















              The following options will perform equally, their differences are time, cost, and thickness of the subfloor. Best case scenario you'll still have a 3/4" subfloor, worst case you'll have 1 1/4" (sorted most economical in cost/time to least):




              1. Lay 1/2 or (preferably) 5/8 over the existing floor. It's simple, and should provide enough strength with the existing strips to support tile.


              2. Replace the strips that are weakened (you should be able to find a piece of 3/4 that would fit the space. All strips should cross a minimum of three joists for strength.
                Follow up by laying 1/2" or 5/8" on top.


              3. Remove and replace. This is a challenging option, those strips probably cross the entire house, that this means is that the walls are resting on the strips. When you remove the existing strips it will cause sagging in adjacent rooms so you'll need to at least block out beneath the walls/between joists to support the flooring on the other side. You'll also have to block out in between joists, and at the edges where the joists are more than a couple of inches away from the bathroom wall.



              Once you've blocked out the floor reinforcements take a look at the joist spacing.



              Subfloor replacement selection - OSB or Plywood. For tile, plywood is generally recommended by manufacturers over OSB.



              Picking sheathing



              Not all sheathing is created equal, however if you're picking up sheathing grade from a big box store, they hold a respectable graded sheet which is what I'm going to base the rest on.



              What's your joist spacing? What is the nominal size of the joist?
              If it's 18" and 2x8 (most likely case) or greater, you can probably get away with one 3/4, but I'd recommend 2-5/8" cross installed. If it's 16" and under, you'll be fine with a single 3/4"



              If you're going to lay sheathing on the existing floor, you need a minimum (emphasis on minimum) of 3/8". Whether it's T&G or not, anything less than 3/8 is a waste of money as it's not structural.



              Install



              Either t&g, or square edge is fine, what's important is to space them 1/8" apart (use something that's credit card thickness for spacing). Ideally glued in the seam if it's t&g, and to the joist using an ASTM D3498, or APA AFG-01 conforming adhesive (PL-400/Premium, Lumber Lock, AdvanTech for example). before applying the glue, make sure all surfaces are clean and dry.



              Cutting and Blocking



              There aren't any perfect videos, however for the preparation this video has great considerations:
              https://www.youtube.com/watch?v=CgWtHSsww-4



              Notes about blocking, use a minimum of 2x6. If you're going to use screws, I'd suggest structural screws like these



              Otherwise 16d common nails will work.



              End product should look like this





              Sources



              Ditra install guideline (they guarantee replacement if tiles crack so they'll give safe numbers) bottom of page 7 for your setup:
              https://sccpublic.s3-external-1.amazonaws.com/sys-master/images/h71/h71/8858545389598/DITRA%20Installation%20Handbook.pdf



              Page six for the bare minimum required for sheathing based on joist spacing: http://www.tolko.com/system/resources/W1siZiIsIjIwMTcvMDEvMTgvMTBfMjFfMzNfMjM3X0FQQV9FbmdpbmVlcmVkX1dvb2RfRmxvb3JfU3lzdGVtc19Db25zdHJ1Y3Rpb25fR3VpZGUucGRmIl1d/APA-Engineered%20Wood%20Floor%20Systems-Construction%20Guide.pdf







              share|improve this answer














              share|improve this answer



              share|improve this answer








              edited 8 mins ago









              Xen2050

              35429




              35429










              answered 3 hours ago









              ChrisChris

              38416




              38416













              • What does "block out in between joists, and at the edges" mean, or look like?

                – Xen2050
                1 hour ago











              • @Xen2050 I've added details, I was hoping for a good video on it, however they are all missing key points which I've commented on, and added a picture for reference.

                – Chris
                40 mins ago



















              • What does "block out in between joists, and at the edges" mean, or look like?

                – Xen2050
                1 hour ago











              • @Xen2050 I've added details, I was hoping for a good video on it, however they are all missing key points which I've commented on, and added a picture for reference.

                – Chris
                40 mins ago

















              What does "block out in between joists, and at the edges" mean, or look like?

              – Xen2050
              1 hour ago





              What does "block out in between joists, and at the edges" mean, or look like?

              – Xen2050
              1 hour ago













              @Xen2050 I've added details, I was hoping for a good video on it, however they are all missing key points which I've commented on, and added a picture for reference.

              – Chris
              40 mins ago





              @Xen2050 I've added details, I was hoping for a good video on it, however they are all missing key points which I've commented on, and added a picture for reference.

              – Chris
              40 mins ago











              0














              Cost is the biggest issue. Replacing it completely is the obvious choice. That's expensive. You can easily add 1/4" ply glued and screwed down and it will be totally structurally safe. You may however get squeaky, spongey floors. If you can fit it in your budget redo it with a new flooring material especially if you are going with tile.



              It's often less expensive to do it right once.






              share|improve this answer








              New contributor




              Joe Fala is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
              Check out our Code of Conduct.

























                0














                Cost is the biggest issue. Replacing it completely is the obvious choice. That's expensive. You can easily add 1/4" ply glued and screwed down and it will be totally structurally safe. You may however get squeaky, spongey floors. If you can fit it in your budget redo it with a new flooring material especially if you are going with tile.



                It's often less expensive to do it right once.






                share|improve this answer








                New contributor




                Joe Fala is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
                Check out our Code of Conduct.























                  0












                  0








                  0







                  Cost is the biggest issue. Replacing it completely is the obvious choice. That's expensive. You can easily add 1/4" ply glued and screwed down and it will be totally structurally safe. You may however get squeaky, spongey floors. If you can fit it in your budget redo it with a new flooring material especially if you are going with tile.



                  It's often less expensive to do it right once.






                  share|improve this answer








                  New contributor




                  Joe Fala is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
                  Check out our Code of Conduct.










                  Cost is the biggest issue. Replacing it completely is the obvious choice. That's expensive. You can easily add 1/4" ply glued and screwed down and it will be totally structurally safe. You may however get squeaky, spongey floors. If you can fit it in your budget redo it with a new flooring material especially if you are going with tile.



                  It's often less expensive to do it right once.







                  share|improve this answer








                  New contributor




                  Joe Fala is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
                  Check out our Code of Conduct.









                  share|improve this answer



                  share|improve this answer






                  New contributor




                  Joe Fala is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
                  Check out our Code of Conduct.









                  answered 7 hours ago









                  Joe FalaJoe Fala

                  3518




                  3518




                  New contributor




                  Joe Fala is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
                  Check out our Code of Conduct.





                  New contributor





                  Joe Fala is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
                  Check out our Code of Conduct.






                  Joe Fala is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
                  Check out our Code of Conduct.






























                      draft saved

                      draft discarded




















































                      Thanks for contributing an answer to Home Improvement Stack Exchange!


                      • Please be sure to answer the question. Provide details and share your research!

                      But avoid



                      • Asking for help, clarification, or responding to other answers.

                      • Making statements based on opinion; back them up with references or personal experience.


                      To learn more, see our tips on writing great answers.




                      draft saved


                      draft discarded














                      StackExchange.ready(
                      function () {
                      StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fdiy.stackexchange.com%2fquestions%2f157845%2fhow-to-repair-replace-old-tongue-and-groove-plank-subfloor-in-bathroom%23new-answer', 'question_page');
                      }
                      );

                      Post as a guest















                      Required, but never shown





















































                      Required, but never shown














                      Required, but never shown












                      Required, but never shown







                      Required, but never shown

































                      Required, but never shown














                      Required, but never shown












                      Required, but never shown







                      Required, but never shown







                      Popular posts from this blog

                      Fluorita

                      Hulsita

                      Península de Txukotka